World Demolition Awards shortlists - Collaboration

C&D Demolition Consultants
Country United Kingdom
Project Demolition and regeneration of the listed Fort Regent Complex

Client States of Jersey
The States Assembly of Jersey decided to introduce external expertise to help oversee a complex demolition project and appointed C&D Demolition Consultants.

COLLABORATION C&D Demolition

The list of challenges was stacked against the project team however, following the pre-tender works carried out by C&D the following challenges were overcome:

  • Sheer cliffs to both the east and west ramparts
  • Grade 1 listed Fort Regent
  • Largest asbestos removal in the island’s history
  • Live car parks to all gable ends of the site
  • Covid 19
  • Lack of experience and machinery on the island.

There was also a children’s nursery located just 2 m (6 ft) from the tunnel entrance that would need to be used to remove demolition materials on the cable car scheme along with the main swimming pool demolition.

Despe/ERM
Country Italy
Project Exxon Mobil Refinery – Notre Dame De Gravenchon – Block 201
Client Esso Rafinage/Exxom Mobil (EP&S) Division
ExxonMobil operates a large refinery near the Normandy coast of France. One of the original 1930s structures was a steam and power plant containing four boilers/economisers and two turbine sets. The power plant had been non-operational since the 1990s but was located next to operating refinery assets. It required decontamination and demolition.

COLLABORATION Despe

Key aspects were protection of very close operational refinery assets, asbestos decontamination and demolition/dismantling including use of protective “curtains” and remote operated suspended “spider” for asbestos roof materials removal, all close to operating refinery areas.

To visualise this, the main boiler house was like a big reinforced concrete box with four old boilers inside, full of asbestos, with all high-level areas in poor condition or inaccessible – 20 m (65 ft) to the east there was an operating oils production plant so no dust could be created and 10 m (32 ft) to the west there was a laboratory where no vibration was allowed.

In one year of work, in this abandoned power station within an operating refinery, the main boiler house with four boilers, a turbine room, pump house and two cooling towers were demolished.

Erith Contractors/Inovyn
Country United Kingdom
Project Inovyn, Runcorn – Framework
Client Inovyn
Following the success of Erith’s initial project at Inovyn, the asbestos removal, decontamination, deplant, dismantling and site clearance of the chloromethanes facilities and an intensive qualification process, Erith has been appointed to a 10-year framework to carry out decommissioning across the strategic site in Runcorn.

COLLABORATION Erith

Projects carried out in the past year have included the removal of assets in the Western Point Power Station pump house, involving the use of specialist divers to remove the redundant drum screen and platforms that were located underwater, the demolition of the waste brine treatment plant and the Weaver stock sheds, and the removal of mercury cells from J Unit.

The companies’ methodology addressed several challenges, including COMAH (Control of Major Accident Hazards) regulations, existing services, temporary works requirements and ecology considerations.

Flesan
Country Chile
Project Demolition of 7b Infiernillo Phase Infrastructures
Client Anglo American Los Bronces
The demolished building, located in the Los Bronces Mine of Anglo-American Chile, it was built mainly in metal and concrete. Due to the coming winter season the Andes, controlled demolition through explosives was chosen.

COLLABORATION Flesan

Due to the high demands of Chilean mining, an alliance was formed with Jet Demolition to work with high worldwide standards and with Enaex in relation to special procedures to obtain permits.

Due to the power supply substation close to the mine, a thorough calculation report was developed. Previous work from blasting was performed, along with possible risks assessments and safety and environmental mitigation measures.

Before detonation, only structural columns and beams were left, removing all lightweight structures in front of the building.

An impact containment absorption system was installed along with geotextile to avoid particles and elements.

Finally, everything turned out according to plan, without incidents or accidents.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, Demolition & Recycling International Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
CONNECT WITH THE TEAM
Leila Steed Editor, Demolition & Recycling International Tel: +44(0) 1892 786 261 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
Simon Kelly Group Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA