Costello Dismantling’s ‘surgical’ demolition

Premium Content

USA-based contractor Costello Dismantling is helping one of its customers, the utility company National Grid to create a new infrastructure to address efficient delivery of new energy sources. Part of this involved the recent demolition of the Walnut Street substation in the town of Haverhill, Massachusetts, in the north east of the country.

Built in the early 1920s, the facility was a historic electric switch house and distribution centre for that region of National Grid service, occupying three floors of a concrete building with brick façade.

Costello Dismantling - Walnut St substation Demolition of the roof at Walnut Street. Photo courtesy Cara Duplessis

For Costello Dismantling, the major challenge in the demolition plan was a 1930s residential building only 1.2 m (4 ft) away from the substation.

The substation towered over the house and any resulting debris from demolition would certainly damage the neighbouring property. Instead, Costello submitted a demolition and remediation plan to National Grid for review. After considerable discussion between contractor, client and the neighbours, a fully comprehensive plan was ready for implementation.

Costello said the building was largely free of environmental contaminants before the start of the contract, but small amounts of asbestos and – typical for this type of building – PCB (polychlorinated biphenyl) contamination remained. The company removed the most difficult to manage PCB material using robotic grinding equipment in negative air containment, as well as traditional concrete chipping by hand. It also abated asbestos-containing waterproofing from the roof flashing prior to demolition.

Costello Dismantling Walnut St substation The project reaches the third floor. Photo courtesy Cara Duplessis

To eliminate dust and protect the neighbouring building, subcontractor Commonwealth Scaffold erected a three-story scaffolding system that wrapped around the side of the building closest to the adjacent house.

For safety reasons, Costello developed what it described as a “surgical” demolition plan that entailed careful demolition of the critical western bay with a robotic Brokk demolition tool.

This former substation was dismantled with no accidents, no damage to the adjacent building, and minimal disruption to the mostly residential neighbourhood.

Latest News
Volvo CE and Metzner in first all-electric deconstruction project
Volvo Construction Equipment (Volvo CE) and Metzner Recycling has completed the world’s first zero-emission industrial-scale deconstruction
Metso inaugurates hydrogen-powered plant
Pre-reduction pilot plant uses hydrogen as the sole reducing agent
Steelwrist launches “next-generation” tiltrotator control system
Sweden-based OEM Steelwrist has unveiled QuantumConnect, its new tiltrotator control system platform
CONNECT WITH THE TEAM
Lewis Tyler Editor Tel: +44(0) 7566 799988 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

If You’re Not Here, You’re Catching Up.

Experts from every continent come together at the The World Demolition Summit to share how they’re solving the challenges you’ll face tomorrow. Learn from failures, near-misses, and creative recoveries that shaped some of the industry’s biggest projects.

📅 3-5 November 2025
📍 Nashville, TN
🎟️ Conference, Networking & Awards Dinner

Count me in!