Skanska’s Francis Scott Key Bridge recovery work worth $50m
11 June 2024
Skanska has revealed that recovery and salvage work at the collapsed Francis Scott Key Bridge in Baltimore, USA, is worth a total of US$50 million.
The company started debris removal, disposal, and clean-up at the site in April 2024 and is due to complete works in July this year.
The bridge collapsed on 26 March after being struck by a container ship.
According to the US Army Corps of Engineers (USACE), which has overseen a…