Read this article in 中文 Français Deutsch Italiano Português Español
The project that won the World Demolition Award (Contracts under $1 million)
02 December 2025
Total Controlled Demolition Services Ltd undertook the internal deconstruction and enabling demolition works at Heaps Rice Mill, a Grade II listed warehouse in Liverpool’s Baltic Triangle.
Photo: Total Controlled Demolition
Built in the late 18th century, the mill is a significant part of Liverpool’s industrial heritage.
The project involved removing the internal structure while fully preserving the external façade and roof, within a busy urban environment.
Challenges and constraints
The project presented multiple technical and logistical challenges.
The site was tightly constrained, surrounded by residential apartments, commercial businesses, and creative studios, leaving almost no external working space.
Internally, many floors were structurally compromised and unsafe for personnel or traditional machinery.
As a listed building, all demolition works had to minimise vibration, dust, and noise.
Standard demolition methods were unsuitable, and every step had to be carefully planned and approved in consultation with conservation specialists.
Equipment and approach
To address these constraints, Total deployed in-house Brokk 110 robotic excavators. These compact, remote-controlled units were craned into position using bespoke lift plans, allowing the team to access structurally compromised and confined areas safely.
Operating from suspended decks, supported slabs, and custom platforms, the robots enabled precise removal of internal structures without exposing personnel to risk or affecting the building’s external shell.
Their low-vibration and low-noise performance also ensured compliance with heritage requirements.
Suspended platforms were used to provide access where floors were unsafe, and all work was carefully coordinated to maintain stability and protect the retained façade.
By combining robotic demolition with engineered working platforms, the team could carry out delicate internal dismantling while minimising risk to both workers and the structure.
Collaboration and safety
Collaboration was a central part of project delivery. Total’sdemolition engineers worked closely with structural consultants, conservation officers, and the client’s project team from the outset.
Daily briefings, real-time risk assessments, and regular review meetings ensured all activities were aligned with safety and heritage requirements.
Local stakeholders, including residents and nearby businesses, were kept informed throughout the project, and noise and vibration were actively monitored to maintain transparency and minimise disruption.
Safety performance was a priority. The project was completed with zero incidents or accidents. Health and safety protocols were continuously updated to reflect evolving site conditions, including weekly safety audits and strict compliance with CDM regulations.
Photo: Total Controlled Demolition
The use of robotic equipment also contributed to keeping personnel out of high-risk areas, supporting Total’s commitment to a safe working environment.
Programme and budget management
While safety and heritage compliance were the primary focus, the project was also delivered with commercial discipline.
Total leveraged in-house capabilities—including machinery, planning, and health, safety, environment, and quality management—to reduce reliance on external contractors, manage risks, and improve efficiency.
The team provided regular cost updates, transparent reporting, and risk management to the client.
Despite the complexity of the project, all works were completed ahead of programme and within budget, allowing the wider redevelopment to progress as planned.
Outcome
The client praised Total for professionalism, collaboration, and the ability to deliver a complex project in a high-risk, heritage-sensitive environment.
The successful completion of the internal deconstruction while preserving the external façade and roof demonstrates a balance of innovation, precision, and respect for historical structures.
Key project highlights
The internal demolition of Heaps Rice Mill was completed while fully preserving the building’s external façade and roof. Brokk 110 robotic excavators were used to safely access structurally compromised areas, operating from suspended decks and custom platforms.
Suspended platforms allowed work where floors were unsafe, and all demolition activities were carefully coordinated to maintain structural integrity.
The project was completed with zero incidents, supported by continuous monitoring and updated safety protocols. Works were delivered ahead of programme and within budget, demonstrating strong planning and financial management.
Noise, vibration, and dust were strictly controlled, and local stakeholders were kept informed throughout, ensuring minimal disruption to the surrounding community.
CONNECT WITH THE TEAM

