Running rubble

Premium Content

10 April 2008

UK contractor Squibb and Davies is using a novel approach to remove demolition debris from a site it is currently working on in central London. The company is demolishing an office block on an enclosed site behind the Fenwick shop on Bond Street.

The office block is being brought down brick by brick but there is no vehicular or other access to the site to allow for the removal of the demolition debris. Squibb and Davis, with the assistance of materials handling expert Robson, has therefore run a curved 30 m (99 ft) long conveyor mounted inside a sound-proof temporary tunnel that runs through the women's fashion department in the Fenwick shop. The conveyor is curved to avoid a number of obstacles.

The conveyor can carry up to 60 tonnes of rubble per hour, and emerges high up on the front of the Fenwick building, with a moveable delivery chute feeding the rubble into trucks for transport away from the site, to minimise impact on traffic flow on the street outside.

Latest News
Total Controlled Demolition begins dismantling at Airbus facility
“Technically challenging” project  is next to active runway
15,000 tonnes of Sizewell A concrete finds new use
Concrete repurposed for nearby Sizewell C site
Project report: Robot used for power plant demolition
Sarens and Tadano carry out Dutch demolition project
CONNECT WITH THE TEAM
Lewis Tyler Editor Tel: +44(0) 7566 799988 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA
Demolition & Recycling International and Construction Briefing Newsletter

Your Industry Brief: Construction, Demolition & Recycling

Stay ahead with the latest industry insights, project updates and expert analysis — straight to your inbox.

It’s free, relevant and quick to sign up.

Sign me up