From top to bottom with Doka in Cologne

Premium Content

02 October 2020

Germany-based formwork specialist Doka is helping in the demolition of Cologne’s landmark former “Deutsche Welle” building, which is scheduled for next year.

Deutsche Welle_02 web

Doka was responsible for pre-assembling the platform and enclosure elements

Originally, the towers of the former radio studio were to be blasted into the ground. However, for various reasons, the plan was changed and the 138 m (453 ft) high towers would be dismantled from top to bottom.

Work began in May 2019 and to ensure that dismantling could progress safely, the contractor called on Doka’s expertise. Doka planned and assembled the protective screen enclosure and trained the team from demolition company BST Becker Sanierungstechnik to use the automatic climbing technology.

Formwork experts are generally called in during construction of concrete buildings, not for tearing them down. However, Doka says its Xclimb 60 automatic climbing formwork and protection screen are suitable for dismantling structures as well as building them.

Deutsche Welle_05 web

As the protection screen climbs downwards, the storeys are removed step by step (both photos courtesy of Doka)

The protection screen Xclimb 60 enclosed the entire demolition area, sheltering the BST Becker team from wind and weather. Rubber lips cut to fit perfectly between the protection screens and buildings created an integrated seal to prevent small parts, debris and dust from falling down, while the system also hugely reduced noise emissions.

The platform and enclosure elements were pre-assembled from detailed plans into large transportable units by Doka’s service teams.

On-site, Doka’s pre-assembly team handled the final assembly and suspended the system on the building.

Despite several weeks of very high temperatures, the assembly was completed in under six weeks with no complications. Also present on site were the Doka instructors, who trained the construction site team for the automatic climbing system.

“As a demolition firm, we had virtually never come across a need for formwork before,” explains Michael Wagner, foreman for BST Becker Sanierungstechnik.

“However, the Doka team were there to answer all our questions about the processes and supported us in every way.”

The enclosure, façades and buildings worked their way downwards step by step, reaching the ground in August.

Demolition is scheduled to finish in 2021, creating space for a new residential complex with 700 apartments.

Latest News
UK watchdog proposes even higher duty on Chinese excavators
UK trade watchdog the Trade Remedies Authority (TRA) has proposed upping anti-dumping duties on imported Chinese excavators to as much as 80.16%
Volvo CE and Trimble eliminate extra hardware in new excavator tie-up
Volvo Construction Equipment and Trimble have developed a fully integrated excavator machine control system set to be introduced to select machines in Q1 of 2027
FOCUS: The trends and challenges facing the European demolition industry
Europe’s demolition sector continues to evolve as infrastructure investment, urban regeneration and circular economy targets reshape priorities
CONNECT WITH THE TEAM
Neel Madsen
Neel Madsen Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Peter Collinson VP Sales Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA