Explosive collapse sets up platform’s demolition phase

The Ninian North offshore platform has been successfully collapsed using explosives in a decommissioning process at the Dales Voe facility in Shetland, off Scotland.

Ninian North offshore platform The demolition phase of Ninian North has a recycling target of 97%

Veolia and Peterson, who operate Dales Voe, said the collapse “moves decommissioning in Shetland to the next level” and that the site was “one step closer to becoming a centre of innovation for recycling structures from the North Sea.”

The platform is a 14,200 t steel structure that was delivered on eight legs each around 30 m (98 ft) high.

To significantly reduce the risk of working at height, and to allow for remote demolition with specialist excavators, extensive planning with key stakeholders resulted in the explosive collapse to bring the platform closer to the ground.

The platform was successfully collapsed on 5 June, having undergone decontamination and the removal of hazardous materials by Velia’s decommissioning team since it arrived at Dales Voe last August.

It is expected that the demolition phase – which has a recycling target of 97% - will last several months.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, Demolition & Recycling International Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
CONNECT WITH THE TEAM
Leila Steed Editor, Demolition & Recycling International Tel: +44(0) 1892 786 261 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
Simon Kelly Group Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA