End of the line for Mansfield Brewery

20 June 2008

Cuddy Group is using high reach excavators to demolish the defunct Mansfield Brewery

Cuddy Group is using high reach excavators to demolish the defunct Mansfield Brewery

The eight storey main brewery building at the defunct Mansfield Brewery, UK, which was closed in 2001, is now being demolished by workers from Cuddy Group. Mansfield District Council is redeveloping the site to create a new six acre office, leisure and residential development.

Cuddy’s 12 man team is using high reach excavators and 30 and 50 tonne machines carrying demolition shears to demolish the steel and brick structure, after which they will then move on to demolish the brewery’s 42 m (138 ft) chimney.

The full demolition contract, expected to last for 16 weeks, is worth £200,000 (US$390,000). Cuddy first carried out asbestos removal before commencing the demolition phase of the contract.

The whole project is expected to result in 20,000 tonnes of demolition debris. Cuddy will recycle all steel and wood, and crush brick and concrete using its own mobile crushing equipment for use as backfill on the site, with any surplus being transported for use on other sites. Cuddy has a stated policy of recycling 95% of all demolition debris on its projects.

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, Demolition & Recycling International Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
CONNECT WITH THE TEAM
Leila Steed Editor, Demolition & Recycling International Tel: +44(0) 1892 786 261 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
Simon Kelly Group Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA