In March 2022, after a fire engulfed a 102,000 sq m (1.1 million sq ft) distribution centre in Indiana, USA, local authorities called Casey-Bertram to provide immediate support to the fire department.

A short time later, the Indianapolis-based demolition contractor was tasked with the teardown of several of structure’s concrete pre-cast panels, which measured 14.3 m (47 ft) tall and were situated within 9.1 m (30 ft) of critical utility systems that supported an adjacent distribution centre with over 1,000 employees.

To complete the challenging project Casey-Bertram used a Kobelco SK300 with a 15 m high reach front and a LaBounty multi-demolition processor (MDP 20R), both of which were recommended by Ohio-based specialty equipment dealer Company Wrench. 

Find out how Casey-Bertram met the challenge: read our Site Report here!

The challenges of a high reach demolition When a US contractor needed a high reach excavator, it contacted Company Wrench

CONNECT WITH THE TEAM
Lewis Tyler Editor Tel: +44(0) 7566 799988 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA

If You’re Not Here, You’re Catching Up.

Experts from every continent come together at the The World Demolition Summit to share how they’re solving the challenges you’ll face tomorrow. Learn from failures, near-misses, and creative recoveries that shaped some of the industry’s biggest projects.

📅 3-5 November 2025
📍 Nashville, TN
🎟️ Conference, Networking & Awards Dinner

Count me in!