Redcar steelworks furnace demolished

Demolition specialist Thompsons of Prudhoe has brought down the 111 m (365 ft) tall blast furnace at the SSI Redcar steelworks in the north of England

The Redcar Blast Furnace The Redcar Blast Furnace. (Photo: Teesworks)

The Redcar blast furnace - which was built in 1979 and was once said to be the second largest of its kind in Europe - had been in operation for nearly a century but closed in 2015 after the site’s owner Sahaviriya Steel Industries UK entered liquidation.

It was demolished yesterday (Wednesday 23 November, 2022) via a controlled explosion that incorporated the furnace’s associated casting houses, charge conveyors and dust catcher. 

The blow down is the latest of a number of major demolition works to be carried out at the site, which is being redeveloped to form part of a 1,821 ha (4,500 acre) manufacturing hub.

While the site’s Sinter Plant was taken down in August, last month saw Thompsons use 1.6 t of explosives to carry out the demolition of the Basic Oxygen Steelmaking (BOS) plant (part of SSI Redcar steelworks).

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, Demolition & Recycling International Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
CONNECT WITH THE TEAM
Leila Steed Editor, Demolition & Recycling International Tel: +44(0) 1892 786 261 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
Simon Kelly Group Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA