UK contractor Cuddy Group used explosives during the final stage of an 18 month, £5 million (US$9.8 million) contract to demolish a former Nippon Electric Glass facility, Trident Park, in Cardiff Bay, Wales.

Cuddy blew down the site's batching plant – a structure 40 m (132 ft) high, 40 m wide and 25 m (82 ft) deep that had been used to process materials used in the manufacture of television screens.

It took Cuddy's eight man team six months to prepare for the blowdown, with the final eight weeks of the job involving strip out and preweakening. The blowdown was designed so that 18 of the structure's legs were basted at intervals of 25 milliseconds to spread the effect of the blast over half a second. This significantly reduced vibration, noise and dust levels. Cuddy intends that the 5,000 tonnes of concrete rubble and steel scrap that resulted from the job will all be recycled.

The site is being redeveloped by Welsh property developed PMG, who bought the site for £18 million (US$35 million), into a major trade park for South Wales.

Latest News
Celebrating the WDA 2026 winners!
The winners of the World Demolition Awards 2026 have been unveiled with trophies presented to the highest scoring entrants at the annual gala dinner.
World Demolition Summit under way in sunny Madrid
Organisers have welcomed 435 demolition professionals from across the globe to the industry event
Terex to acquire Keestrack
Acquisition expands Terex Materials Processing’s crushing and screening portfolio
CONNECT WITH THE TEAM
Neel Madsen
Neel Madsen Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Peter Collinson VP Sales Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA