The deaerator bay and turbine hall at the former Aberthaw B power station in the Vale of Glamorgan were taken down on 14 February 2026.

Power station in the process of being demolished by explosives Aberthaw power station (Image credit: CCR Energy)

Explosive engineering specialists Precision Demolition Company (PDC) and Ertih Contractors have successfully completed the controlled demolition of the structures for CCR Energy Ltd, an entity established by the Cardiff Capital Region to lead the transformation of site.

The turbine hall was one of the largest remaining structures on the 500-acre Aberthaw site which closed in March 2020.

Extending for over 230 metres in length and constructed from substantial reinforced concrete and structural steel, the building historically housed the main turbine and auxiliary plant used in electricity generation.

A key part of the wider demolition and site-enabling programme, the blowdown was carried out safely and precisely by PDC and Erith, supported by on-site safety teams and delivered in line with agreed safety and environmental controls.



“The turbine hall was a large and technically complex structure, requiring detailed engineering assessment and a rigorous, safety-led approach,” said Andy Dyson, Erith’s operations director.

“Our team worked closely with CCR Energy and PDC to deliver a controlled and successful demolition, and we are proud to be contributing to this important phase of the site’s transformation.”

Cormac McLean, managing director of PDC, added, “The controlled demolition of a structure of this scale and complexity requires extensive modelling, precise sequencing and close coordination.

“The turbine hall blowdown was the result of months of preparation, and we are pleased to have delivered a safe and accurate outcome that enables the next phase of redevelopment at Aberthaw.”

McLean also said that this project marks a notable moment for PDC, which carried out the explosive demolition of Aberthaw A power station on the same site almost three decades ago.

Latest News
Supreme award winners 2025 to present Best of the Best project
DDM will showcase the project that took home the top trophy at the World Demolition Awards last year
New Kobelco dealer appointed for southwest France
Newly founded ALMAT takes on Kobelco brand across a territory in southwest France
Controlled deconstruction at height
Hear first-hand at WDS 2026 from the team behind the complex, high-risk removal of an elevated water tank 
CONNECT WITH THE TEAM
Neel Madsen
Neel Madsen Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Peter Collinson VP Sales Tel: +44 (0) 1892 786220 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA