VIDEO: PDC and Erith demolish turbine hall at Aberthaw
23 March 2026
The deaerator bay and turbine hall at the former Aberthaw B power station in the Vale of Glamorgan were taken down on 14 February 2026.
Explosive engineering specialists Precision Demolition Company (PDC) and Ertih Contractors have successfully completed the controlled demolition of the structures for CCR Energy Ltd, an entity established by the Cardiff Capital Region to lead the transformation of site.
The turbine hall was one of the largest remaining structures on the 500-acre…