€230 million Swiss rail tunnel project for Implenia

Implenia has been awarded a significant railway infrastructure project in Switzerland.

A visualisation of the proposed Tunnel Ligerz project to be undertaken by the IBD joint venture A visualisation of the proposed Tunnel Ligerz project to be undertaken by the IBD joint venture. Image: Implenia

The Swiss Federal Railways (SBB) has awarded an Implenia-led joint venture a €230 million contract for a significant lot on the country’s Ligerz-Twann rail line expansion project.

The Lot 2 contract will see Implenia and its partners Bernasconi and De Luca construct a 2.1km-long double-track tunnel (Tunnel Ligerz), with around 1,850m being excavated using mining techniques and the remaining 250m through cut-and-cover methods.

The joint venture vehicle, IBD, and it will install concrete lining and railway technology within the tunnel, as well as constructing four escape tunnels and a 114m-long viaduct for a highway exit, along with other supplementary structures.

Significant construction challenges

The construction process will involve the transportation of excavated material by ship, and the existing railway line will be dismantled and redesigned to accommodate the new developments.

The project poses significant challenges for the construction team, due to its location in protected areas.

The region falls under the Federal Inventory of Landscapes and Natural Monuments (BLN), and the villages of La Neuveville, Chavannes, Ligerz, and Twann are listed as part of the Federal Inventory of Swiss Heritage Sites of National Importance (ISOS).

Christian Späth, head of Implenia’s civil engineering division, “We are looking forward to carrying out this large and complex rail infrastructure project together with our joint venture partners and once again demonstrating our longstanding experience and expertise in this area. We wish the entire project team an accident-free construction period.”

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, Demolition & Recycling International Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
CONNECT WITH THE TEAM
Leila Steed Editor, Demolition & Recycling International Tel: +44(0) 1892 786 261 E-mail: [email protected]
Peter Collinson International Sales Manager Tel: +44 (0) 1892 786220 E-mail: [email protected]
Simon Kelly Group Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA